Office relocation checklist for small Sydney businesses

Short answer

Give a small office move eight to twelve weeks. The dates that actually control everything are your lease end and make-good, and your internet connection at the new address. Book the removalist and the building lift once those two are locked. Everything else can be arranged around them.

Key takeaways

  • Internet is the long pole, not the furniture. A new business connection can take weeks. Order it first.
  • Read your make-good clause before you do anything else. It can cost more than the move.
  • Book the lift and loading dock early in both buildings. Sydney commercial buildings ration them.
  • Move Friday night or Saturday morning so you lose a weekend rather than a trading day.
  • An asset register pays for itself the moment you decide what not to take.
  • Label by destination, not by contents. Nobody unpacking cares what is in the box, only which desk it goes to.
What is in this guide 9 sections

How long a small office move takes

Eight to twelve weeks is realistic for a 5 to 30 desk office. You can do it in four if you have to, but you will pay for the compression somewhere, usually in a rushed make-good or an internet connection that is not live on the Monday.

Here is the shape of it. Adjust to your own lease dates rather than treating this as gospel.

When What has to happen Why it is in this slot
12 weeks out Read the lease. Confirm the make-good obligation and the exit date. Sign the new lease. Make-good scope can change your budget and your timeline more than anything else here.
10 weeks out Order the internet and phone service at the new address. This is the single longest lead time in the whole project.
8 weeks out Floor plan for the new space. Asset register of what moves, what goes, what gets replaced. You cannot get an accurate removal quote without knowing what is actually moving.
6 weeks out Get removal quotes. Book the mover. Book lifts and loading docks at both ends. Building access is rationed and books out, especially for weekends.
4 weeks out Notify staff, clients, suppliers, couriers. Start the address change list. Enough lead time for people to update records before the switch.
2 weeks out Order boxes and labels. Confirm the IT plan. Book any electrical or data work at the new site. Packing materials on site early means staff can pack in gaps rather than in a panic.
1 week out Staff pack personal items and desk contents. Label everything by destination. People pack better with a week than with an evening.
Moving weekend Move, set up IT, walk through both sites. Lose a weekend instead of a trading day.
Week after Make-good the old site. Return keys and access cards. Close the lease out. Rent usually keeps running until make-good is accepted.

First: your lease and the make-good clause

Before you look at a single box, read the exit terms on your current lease. Australian commercial leases almost always carry a make-good clause, and it is the part that surprises people.

Make-good means restoring the premises to an agreed condition when you leave. The NSW Small Business Commission describes it as returning the property in a similar condition to the start of the lease, and notes it can extend to stripping the premises back to bare shell and repainting. Depending on how yours is written, that is anything from a professional clean to removing your fit-out, replacing carpet, and taking out data cabling you installed years ago.

  • Find the clause and read the actual wording. “Original condition” and “as at commencement, fair wear and tear excepted” are very different obligations.
  • Check whether there is a condition report from when you moved in. If there is, that is the benchmark. If there is not, the negotiation is more open than you think.
  • Get the quote early. Make-good works are frequently more expensive than the removal itself.
  • Ask about a cash settlement. Some landlords prefer a payment in lieu, especially if the next tenant is refitting anyway.
  • Confirm when rent actually stops. It is often when make-good is accepted, not when you hand back the keys.
Worth knowing

Your outgoing and incoming lease dates rarely line up neatly. A week or two of overlap is worth paying for. It turns a single frantic weekend into a staged move where you can set up the new space before you empty the old one.

Order the internet before anything else

This is the step that ruins otherwise well-planned office moves, and it has nothing to do with removalists.

A business internet service at a new address is not a same-week job. Depending on what is already installed in the building, it can involve a new connection, in-building cabling, or a site visit, and lead times run into weeks. Order it as soon as the new lease is signed, well before you think about boxes.

  • Ask what is already in the building before you assume a new connection is needed. Existing infrastructure can save you weeks.
  • Get the activation date in writing and build your move date around it, not the other way round.
  • Have a fallback. A mobile broadband service for the first week is cheap insurance against a delayed activation.
  • Sort phone numbers at the same time. Porting a business number takes its own lead time.
  • Do not disconnect the old service until the new one is tested and working.

Build the asset register

An asset register is a list of every desk, chair, screen, cabinet and appliance, and a decision against each one: moves, goes, or gets replaced.

It sounds like busywork. It is the single most useful hour of the whole project, for three reasons.

  1. It makes your removal quote accurate. No mover can price a job properly from “about fifteen desks and some cabinets”.
  2. It stops you paying to move rubbish. Every item you decide against is one you do not pay to lift twice.
  3. It becomes the moving day checklist. You already have the list of what should have arrived.

Walk the office with a phone and photograph as you go. Note anything that is fragile, unusually heavy, or that a manufacturer has to dismantle. Those are the items that determine the crew size and the equipment.

Two Alongshore removalists carrying a large benchtop through a brick warehouse office
Long benchtops and boardroom tables are the items most likely to fail a doorway measurement. Check them before moving day, not on it.

The things people wish they had left behind

  • Archive boxes nobody has opened in five years. Digitise or send them to a document storage facility instead of paying to relocate them.
  • Broken or mismatched chairs. Replacing them costs less than you think and they never improve after a move.
  • Old monitors and towers that are already out of warranty.
  • The second fridge in the kitchen that nobody claims.

Book the lifts, docks and after-hours access

In Sydney commercial and strata buildings this is not a formality, and it catches out anyone who has only moved house before.

  • Service lift booking. Most buildings require it, in writing, days ahead. Some will not release it at all on weekends, which is exactly when you want to move.
  • Loading dock window. Docks often run in fixed slots with a height limit. Check the clearance against the truck.
  • After-hours access. If you are moving on a Saturday, confirm someone can actually let the crew in and that the alarm and security system will allow it.
  • Certificate of currency. Many building managers will not let a removalist on site without seeing their insurance certificate first. Ask your mover for it early and send it through.
  • Do both ends. People book the new building and forget the one they are leaving.

When we quote a small office move we ask about all of this up front, because a booked dock is the difference between a four-hour job and a crew waiting on the street.

Moving an office in the Inner West or on the Lower North Shore?

Small offices are what we do. Our own crew, our own trucks, no subcontractors, and we handle the building paperwork with you.

Tell everyone who needs to know

Start this four weeks out and keep it as a running list rather than trying to remember it all at once.

  • Staff first, and with enough notice that people can sort out their own commute and parking.
  • Clients and suppliers, with the change date stated plainly.
  • Couriers and regular deliveries. These are the ones that keep arriving at the old address for months.
  • Google Business Profile, website, email signatures, invoices, letterhead. The profile matters more than people expect, because it is where most customers actually find your address.
  • ASIC, your accountant, your insurer, your bank. Registered office and public officer addresses may need updating.
  • Australia Post redirection as a safety net for whatever you missed.

Put the new address in your email signature a few weeks before the move with the date it takes effect. It is the cheapest, highest-coverage announcement you have.

IT, and labelling that actually works

Two jobs that decide whether Monday morning is calm or not.

The IT plan

  • Photograph the back of everything before you unplug it. Server rack, comms cabinet, every desk with a docking station. It is a two-minute job that saves an hour each.
  • Bag and label cables per desk rather than throwing them in a communal box. A box of tangled cables costs more time than it saves.
  • Back up before the move, and verify the backup actually restores.
  • Confirm data points and power at the new desks. Discovering there is no network port where a desk is going is a moving-day problem you can solve four weeks early.
  • Set up and test the network first when you arrive, before the furniture is straight.

Labelling by destination

The most common labelling mistake is describing the contents. Nobody unpacking needs to know a box holds stationery. They need to know where it goes.

  1. Number every room and desk position on the new floor plan. Print it and put a copy on the wall at both ends.
  2. Every box gets the destination number, large, on the top and on at least two sides.
  3. Colour-code by area if you have more than a couple of rooms. Coloured tape is faster to read than writing.
  4. Mark the first-morning boxes separately. Kettle, chargers, the router, and whatever reception needs to open.
  5. Staff pack their own desks into their own numbered boxes. They know what matters and it saves you paying for the hours.

If your team genuinely does not have the time, packing and materials can be added to the job. It usually works out cheaper than the trading hours you lose having staff do it badly at the last minute.

The moving weekend run sheet

Move Friday evening or Saturday morning wherever you can. You are trading a weekend for a trading day, and for most small businesses that is an easy call.

The inside of a moving truck packed tightly with blanket-wrapped furniture and trolleys
A tightly packed truck is not just tidy. It is what stops screens and cabinets shifting between two addresses.
  • One person is the contact. Not three. The crew needs a single decision maker on site at each end.
  • That person has the floor plan and directs boxes as they land, rather than sorting them later.
  • Walk the old site before the truck leaves. Every cupboard, every drawer, under every desk, and the kitchen.
  • Check the asset register off as things arrive. This is why you built it.
  • Set up IT and test it before anyone goes home. Finding a dead connection on Saturday is fixable. Finding it on Monday is not.
  • Do a Monday-morning walk-through before staff arrive, so the first thing they see is a working desk.

What it costs and when to hire someone

Office removal pricing depends on the volume, the access at both ends, and whether the job runs after hours. Stairs, long carries from a dock, and a lift you have to share all cost time, which is what you are actually paying for. We quote on the specifics rather than publishing a flat rate, and you can see how we price on our moving prices page.

Reasonable to handle yourselves

  • Under about five desks, ground floor to ground floor.
  • Nothing heavier than a two-person lift.
  • No lift booking, no loading dock, no after-hours access.
  • You have a van and a weekend you are willing to lose.

Worth having done properly

  • Any move involving a service lift, a loading dock or a building manager.
  • Anything you cannot afford to be without on Monday, which for most offices is everything.
  • Long boardroom tables, tall cabinets and anything that needs dismantling and rebuilding.
  • Fragile or valuable items. A large part of our work comes through real estate agents and antique dealers, so careful handling of things that cannot be replaced is the part of the job we are actually known for.
  • You need it done between Friday night and Monday morning with no margin for error.

If archive boxes or excess furniture need to go somewhere other than the new office, arrange that with a storage facility directly and factor the drop-off into the same day. We can move things there as part of the job, but the storage itself is a separate arrangement you will hold with the facility.

Common questions

How far in advance should you plan an office move?

Eight to twelve weeks for a small office. The two dates that dictate everything are your lease exit with its make-good obligation, and the activation date for internet at the new address. Lock those first and plan backwards.

What is a make-good clause?

A term in most Australian commercial leases requiring you to restore the premises to an agreed condition when you leave. It can range from a professional clean to removing your entire fit-out and repainting. Read the exact wording early, because it is often more expensive than the move itself.

Should we move on a weekend?

For most small offices, yes. A Friday evening or Saturday move means you lose a weekend rather than a trading day. Check first that both buildings allow weekend access to the service lift and loading dock, because some do not.

Who do we need to notify when the office moves?

Staff, clients, suppliers and couriers, then your Google Business Profile, website, email signatures and invoices. Also ASIC, your accountant, insurer and bank if the registered address changes. Set up an Australia Post redirection to catch whatever you missed.

Do removalists disconnect and reconnect computers?

We move the hardware, and we take apart and reassemble furniture. Network configuration and getting systems back online is a job for whoever manages your IT. Book them for the same weekend so the two happen in the right order.

How much does a small office relocation cost?

It depends on volume, access at both ends, and whether the work runs after hours. Stairs, long carries from a loading dock and a shared lift all add time, and time is what you are paying for. See moving prices or call 0416 236 209 for a quote on the actual job.

The short version

Read your make-good clause and order the internet first. Those two set your dates. Then build an asset register, get quotes off it, and book the removalist plus the lifts and loading docks at both buildings.

Four weeks out, start telling people. Two weeks out, get boxes on site. Label by destination, not contents. Move over a weekend, set up IT before anyone goes home, and walk through on Monday morning before staff arrive.

Small office moves are our thing

Owner-operated from Balmain since 1989, across the Inner West, the Lower North Shore and the rest of Sydney.

Share this guide

Ask an AI about this guide

Open this page in your assistant of choice for a summary or a follow-up question.

Alongshore Removals

About the author

Matt Burrell owns and runs Alongshore Removals. He grew up in Rozelle, went to Birchgrove Primary and was school captain of Balmain High, joined Alongshore in 2003 as a 19-year-old university student, and took over running the company from founder Jon Green in 2017.

Alongshore has been moving households and small offices across the Inner West, the Lower North Shore and the rest of Sydney since 1989. Every crew member is employed and trained in house. No subcontractors.

More about Alongshore · Small office moves · 0416 236 209

Sources

  1. NSW Small Business Commission, ‘Make good’ and retail leases
  2. NSW Small Business Commission, Retail Tenancy Guide
  3. NSW Government, Retail leases